Context

The UAE Vision 2021 includes the Green Economy for Sustainable Development Initiative. This includes sourcing 75% of Dubai’s power from clean sources by 2050, and 25% from solar power. The Mohammed bin Rashid Solar Park is the largest single-site solar park in the world; it uses an Independent Power Producer (IPP model) and a build-own-operate project structure. The solar park is owned by DEWA, but is being constructed in five phases, with each phase bid for independently by developers.

Problem

  • The UAE has traditionally imported natural gas for its energy needs. However, rising costs made solar power generation more attractive.
  • The Mohammed bin Rashid Solar Park has a lower solar resource compared to similar solar parks under construction. This would typically lead to reduced investor enthusiasm in a solar project.
  • Concentrated solar power (CSP) is still a relatively unproven technology.

Innovation

  • A long-term PPA of 35 years has helped Mohammed bin Rashid Solar Park achieve lower PPA for both CSP and photovoltaic solar power.
  • The park has gradually increased its capacity through five phases between Q3 2014 and Q4 2021, so that it will eventually reach 5GW by 2030 with a total planned investment of USD13.6 billion.
  • The ACWA consortium, which was awarded Phase 2, was a joint Chinese-Saudi effort with close state ties and experience in the solar construction / energy sector.

Stakeholders involved

  • Dubai Electricity and Water Authority (DEWA): The government entity that commissioned and owns the project
  • First Solar: Constructed the first phase (13 MW)
  • ACWA Consortium: A consortium formed of Chinese and Saudi Arabian investors, which constructed Phase 2 (200 MW) and Phase 5

Timeline

Lowering solar PPA  Timeline

Results and impact

  • The 200-megawatt Phase 2 of the project drew a record-low tender tariff of only USD0.589 per kilowatt hour, which is 20% lower than any other unsubsidised PPA for a solar photovoltaic plant
  • The 700-megawatt Phase 4 of the project drew a tender tariff of only USD7.30 c per kilowatt hour, which is the lowest levelised cost of electricity for a CSP plant globally.1
  • Upon completion, the park will reduce carbon emissions by 6.5 million tonnes annually.

Key lessons learnt

  • Exceptionally long PPA timelines (such as 35 years for Mohammed bin Rashid Solar Park’s Phase 4) provide investors with certainty, leading to a lower cost of capital and potentially to correspondingly cheap tariff bids.
  • The falling cost of CSPtowers – 60% in the five years leading to 2018 – has made the technology commercially viable on a large scale. The size of the station may help create economies of scale during construction phases, which can drive down costs and further contribute to PPA cost savings.
  • Building unproven technologies in stages helps to prove viability and allow for technological development that helps lowers cost later in the project lifecycle.



Source link

Home
We will be happy to hear your thoughts

Leave a reply

Best & Lowest Rates of all online shopping Products
Logo
Compare items
  • Total (0)
Compare
0
Shopping cart